Skip to main content

The Queensland Government continues vital reconstruction works on the Captain Cook Highway following damage caused by ex-Tropical Cyclone Jasper. Here’s the latest update to help road users plan ahead.

Traffic Control and Closures

  • No night closures are scheduled for the rest of September or throughout October.

  • Night works may be required from late October through December 2025. Specific dates will be shared closer to the time, depending on weather, site conditions, and construction progress.

Mid-October Traffic Control Changes

  • The single-lane traffic control point south of Oak Beach (about 1.3 km) will move further south, shortening the existing single-lane section.

  • A new single-lane section will be introduced about 3 km north of Ellis Beach to allow work at a major debris flow site.

  • Road users will be guided by Variable Message Signs (VMS) and onsite signage.

  • TMR has coordinated with contractors to ensure these changes do not increase current delays.


Progress of Works

Completed and Ongoing Sites

  • Slope stabilisation completed at 23 sites.

  • Additional work is still required before these sections can fully reopen to two lanes. Tasks include:

    • Drainage restoration

    • Guardrail and signage installation

    • Pavement repairs and line marking

  • These finishing works will be delivered simultaneously across several sites to minimise disruptions.

Ellis Beach to South Wangetti

  • Stabilisation, excavation, and concrete foundation placement for debris barrier installation are underway at major debris flow sites.

  • Culvert repairs continue at the southern end of Ellis Beach.

Turtle Creek Beach

  • Concrete pours and shotcreting are in progress.

  • Key updates include:

    • Mesh installation and shotcreting completed upslope.

    • A concrete retaining structure is being built 600 m north of Turtle Creek Beach.

    • Additional retaining structures are underway at downslope sites treated during emergency works in mid-2025.

    • Stabilisation works have begun upslope, 500 m south of Turtle Creek Beach.


Betterment Works

In addition to reconstruction, nearly $49 million is being invested into betterment works across eight state-controlled roads in Far North Queensland.

These works will:

  • Strengthen local road networks.

  • Reduce future disaster impacts on the community.

  • Include bitumen and drainage upgrades at multiple sections of the Captain Cook Highway.

This funding is part of the jointly funded Commonwealth–State Disaster Recovery Funding Arrangements (DRFA).


Stay Informed